King West Life – Construction Update

admin Uncategorized

The construction phase at the East Liberty site is progressing as planned: the east tower (65 East Liberty St.) has reached the 23rd and final floor with some mechanical work being completed on the rooftop; the middle (75 East Liberty St.) and the west (85 East Liberty St.) towers are following closely behind – reaching 15th and the 5th floors respectively.

The windows are currently being made off-site and the installation has extended to the 11th floor of the east tower.

The following pictures have been taken on Dec 12th.