Construction Update – Framing Near Completion

admin Commercial, Portfolio Updates, Residential Development

Construction for The College At Spadina continues steadily at an impressive rate.  Keeping on pace at approximately 2 stories per month, the structure now stands 13 stories tall out of 15 total floors.  Progress is well on schedule and it is anticipated that the building’s framework will be completed before the year’s end.

Aerial view of 297 College Street, photo taken October 25, 2015


Aerial view of 297 College Street, photo taken October 25, 2015

 

Window and glass installation is also moving quickly, currently reaching up to the 7th floor.

 

Window installation progress, photo taken October 25, 2015


Window installation progress, photo taken October 25, 2015

 

Interim occupancies are projected to commence in Q3 2016, with condominium registration slated for early fall 2016, and final closings expected to occur by the end of October 2016.